Carlisle Southern Link Road

As part of developing an improved road network in and around Carlisle, Cumbria County Council are in the early stages of exploring the possibility of a Southern Link Road for Carlisle. 

The need to improve east to west connectivity has been identified in the Local Enterprise Partnership (LEP)  Cumbria Infrastructure Plan and in Carlisle City Council's recently adopted  Carlisle District Local Plan 2015-2030. The link road would be required to unlock delivery of the planned St Cuthbert's Garden Village.

 

Project Location

If a Carlisle Southern Link Road is developed in the future, the new road would connect Junction 42 of the M6 with the A595 to the west. The route would include new junctions linking existing radial routes into Carlisle and the Garden Village.

The route would include bridges over two main railway lines and the Caldew and Petteril rivers, a network of footways and cycleways and an extensive programme of landscaping and environmental mitigation.

This 8km long road would provide vital infrastructure to relieve congestion in the historic city of Carlisle and provide the access and network capacity to enable the successful and accelerated delivery of St Cuthbert's Garden Village.

Project Development

Cumbria County Council, working with Carlisle City Council, have commissioned Carlisle based transport consultants Capita to develop options for a Carlisle Southern Link Road. The team will undertake key surveys and assessments to work towards the development of route options. Public consultation on the route options will take place in early in 2018. A preferred route option will be identified in Spring 2018 and an Outline Business Case will be prepared to assist in securing Government funding to deliver the Link Road.

Project Objectives

Carlisle Southern Link Road Project Objectives (JPEG 316kb)

Project Timescales

The project is dependent on the availability and securing of funding. It is also dependent on legal statutory processes including the planning permission process and the acquisition of land for the route. If challenges faced by funding and statutory procedures can be dealt with effectively the team are currently working to a date for beginning of construction in 2020.

Carlisle Southern Link Road Project Timeline (JPEG 132kb)

Project Cost and Funding

The cost of the project is unknown at this stage largely because the alignment and location and size of major structures (e.g. bridges) on the route is not yet known. Similar projects have cost between £ 100 million and £ 200 million. Funding for the initial design stages of the project is currently being allocated from Cumbria County Council and Carlisle City Council. The project team is continually looking for funding opportunities from dedicated government funding streams.

Project Environmental Impacts

The impacts on the local environment will be considered within an Environmental Impact Assessment (EIA) which will also inform the project team of features of interest which need to be taken into account. In particular the team will be assessing impacts on the river crossings of the Caldew and the Petteril, listed buildings and the wider landscape.

Look ahead:

April 2018

  • Complete drafting of the consultation report.
  • Complete the Environmental Impact Assessment.
  • Continue to progress preparation of the Outline Business Case.
  • Progress preparation of full submission to the Housing Infrastructure Fund.

Undertaken in:

March 2018

  • Public Consultation closed (9th March) with over 1000 people attending the public exhibition events.
  • Public Consultation assessment of feedback commenced.
  • Land valuation survey completed.
  • Environmental Impact Assessment draft completed and under review.
  • Outline Business Case progressed.
  • Expression of Interest application to the Housing Infrastructure Fund successful.
  • Initial work on full submission to the Housing Infrastructure Fund started.

February 2018

  • Public consultation drop-in events held - two days at Carlisle Racecourse and two days in the Lanes Shopping Centre.
  • Technical assessments to inform a preferred route decision ongoing.
  • Risk workshop held and cost risk analysis undertaken.

January 2018

  • Public consultation launched 26th January.
  • Consultation materials developed including the Consultation Document, Consultation Questionnaire and display materials for public events.
  • Engagement ongoing with directly affected landowners.
  • Route cost estimates developed.

December 2017

  • Route option concepts finalised using updated environmental and traffic data.
  • Environmental Impact Assessment progressed further.
  • Preparation for landowner and public consultation activity in early 2018.
  • Preparation of Consultation documentation.

November 2017

  • Agricultural Land Classification surveys completed.
  • Drainage surveys and field assessment completed.
  • Environmental Impact Assessment progressed using survey results.
  • Design of routes developed following Environmental Impact Assessment feedback.
  • Traffic modelling progressed.
  • Cost estimates started.
  • Joint working forums with St Cuthbert's Garden Village team.

October 2017

  • Ecological, noise and landscape surveys completed. Structural assessments of existing bridges completed.
  • Route options developed in line with emerging constraint assessments.
  • Non-Motorised User (NMU) counts to survey pedestrian, equestrian and cyclist numbers and movements completed.
  • Opportunities for flood alleviation investigated.

September 2017

  • Landowners to the South of Carlisle contacted to agree access for ecological and noise surveys and assessments to help inform the route options.
  • Consultation with regulatory stakeholders including the Environment Agency, Natural England and the Highways Agency to ensure that high level regulatory issues are identified at this early stage of the project.
  • Ecological surveys started.
  • Expression of Interest (EOI) application to the Housing Infrastructure Fund (HIF) submitted. 

August 2017

  • Consultant team (Capita) appointed to take the development of the route options forward.
  • A wide study area identified between Junction 42 of the M6 and Peter Lane.
  • Optional route option corridors developed for the project in line with Transport Assessment Guidance (TAG) and the Design Manual for Roads and Bridges (DMRB).
  • Route option corridors were based on various factors including the required size of the road, impacts on communities, available crossing points for rivers and railways, environmental sensitivity of areas, ability to serve as link to new housing and project costs.

Following a period of scheme development and assessment two route options were identified for a Carlisle Southern Link Road. From 26 January to 9 March 2018 the County Council undertook a period of public consultation to seek the views of the public, and other stakeholders, in order to inform a decision about which of these two route options should be taken forward to the next stage of the development process.

The Carlisle Southern Link Road Consultation Document provides information on the process that was undertaken and the Link Road proposals:

Public Consultation on Route Options for a Carlisle Southern Link Road (PDF 3903kb)

The consultation is now closed.

Plans to investigate a southern link road for Carlisle begin (25 August 2017)

As part of developing an improved road network in and around Carlisle, Cumbria County Council are in the early stages of exploring the possibility of a Southern Link Road for Carlisle. Capita have been commissioned to undertake this early work which is planned to take place between the end of August 2017 and the beginning of October 2017.

Funding bid for southern link road (29 September 2017)

An application was submitted in September 2017 for the Housing Infrastructure Fund (HIF). The 'HIF' is a £ 2.3 billion Fund which offers funding to local authorities on a competitive basis, for infrastructure to support up to 100,000 new homes.

Public invited to have their say on St Cuthbert's Garden Village and Southern Link Road proposals (26 January 2018)

Local residents, businesses and organisations are being asked to have their say on proposals to create a new Garden Village on the south side of Carlisle, and the associated development of a new southern link road, as part of public consultations launched by the city and county councils.

Link road moves to next stage in funding bid (21 March 2018)

 

Plans for the new Carlisle Southern Link Road received a major boost today with news that the scheme has been selected by Government to move to the next stage of its funding bid.

If you have any queries or comments regarding the Carlisle Southern Link Road project, please contact the project team at cslr@cumbria.gov.uk